Conway New Single-Family Home Permit Fees and Submittal Checklist

A new detached one- or two-family dwelling, measured by area under roof including garage and porches.

01

Conway Fee Estimate

Fee Estimate

$

Permit valuation may differ from your construction budget when the city applies its own valuation method.

sq ft

Estimate · Conway, AR

$275.00

Estimated fees for the inputs shown. Conditional items are listed but not added.

Not included in this estimate

Certificate of occupancy; Trade permits (electrical, plumbing, mechanical); utility tap and impact fees, re-inspection fees, and other agency approvals.

Cost of working without a permit in Conway: $500.00Permit fees are multiplied by 2× when work starts before the permit is issued.

Need sealed MEP drawings, permit expediting, or 3 bids from ACLB-licensed contractors in Conway?

Sources and Assumptions

Schedule
Conway Code § 11.16.06 (Ord. O-25-03)
Source reviewed on
October 20, 2026
Assumes
Residential occupancy; $325,000 valuation and 2,200 sq ft as entered.

PermitBasis is an independent planning resource. The issuing authority determines final fees and requirements.

02

Common Project Values

Estimated Conway fees for new single-family home projects at six standard sizes, computed with the same rules as the calculator. Trade permits excluded.

  • Small home

    $150,000 · 1,200 sq ft

    Permit fee $250.00 · review $25.00

    $275.00

  • Starter home

    $225,000 · 1,600 sq ft

    Permit fee $250.00 · review $25.00

    $275.00

  • Standard home

    $325,000 · 2,200 sq ft

    Permit fee $250.00 · review $25.00

    $275.00

  • Family home

    $450,000 · 2,800 sq ft

    Permit fee $308.00 · review $25.00

    $333.00

  • Large home

    $650,000 · 3,800 sq ft

    Permit fee $418.00 · review $25.00

    $443.00

  • Custom home

    $1,000,000 · 5,500 sq ft

    Permit fee $605.00 · review $25.00

    $630.00

03

Central Arkansas Cost Comparison

The same project priced in all eight cities. Valuation-based cities (fee grows with project cost) and square-footage cities (fee grows with floor area) can differ widely for the same building. Full comparison →

04

Conway Submittal Checklist

Required and conditional documents for this project type. Confirm this requirement with the city.

Submittal Checklist0 of 9 ready
  1. Conway permit application

    Submit through Conway Building Permits & Inspections. Include the project address, parcel number, owner, contractor and declared valuation.

    Permit portal ↗
  2. Construction drawings

    Floor plan, foundation plan, wall section and elevations. Plans for one- and two-family dwellings generally do not require an architect's seal.

  3. Site plan or survey

    Property lines, setbacks, easements, building footprint, driveways and drainage. New commercial sites usually go through planning or site plan review first.

  4. Energy code compliance

    REScheck or equivalent showing compliance with the Arkansas Energy Code for the dwelling envelope.

    Arkansas energy code status ↗
  5. Conway Corporation availability and tap letter

    Confirm water and sewer availability and tap or meter fees with Conway Corporation. Tap and impact fees are not part of the building permit estimate.

    Conway Corporation ↗
  6. ADEQ construction stormwater permit

    Conditional

    Sites that disturb one acre or more need coverage under the ADEQ construction stormwater general permit and a stormwater pollution prevention plan.

    Applies when: One acre or more of land disturbance

    ADEQ stormwater ↗
  7. Floodplain development permit

    Conditional

    Required when any part of the work is in a FEMA special flood hazard area. Check the parcel on the FEMA map before design is final.

    Applies when: Parcel is in a mapped floodplain

    FEMA flood map ↗
  8. Arkansas contractor license verification

    Residential projects over $2,000 need an ACLB residential builder or home improvement license, unless the owner is building their own home.

    ACLB license lookup ↗
  9. Trade permits from licensed trades

    Electrical, plumbing and mechanical permits are pulled separately by Arkansas-licensed master electricians, plumbers and HVACR contractors.

Permit office

Conway Building Permits & Inspections

Confirm hours and submittal format with the city before you go.

Inspection Roadmap

  1. 1

    Footing

    After trenches are dug and steel is placed, before concrete

  2. 2

    Foundation / slab

    After under-slab plumbing, vapor barrier and steel, before the pour

  3. 3

    Rough-in: plumbing, electrical, mechanical

    After rough trade work, before walls are covered

  4. 4

    Framing

    After rough-ins pass, before insulation

  5. 5

    Insulation / energy

    After insulation, before drywall

  6. 6

    Trade finals

    Electrical, plumbing and mechanical finals

  7. 7

    Building final

    After all trade finals pass

  8. 8

    Certificate of occupancy

    Issued after the building final; required before move-in

05

Frequently Asked Questions

How much does a new single-family home permit cost in Conway, Arkansas?

Under Conway Code § 11.16.06 (Ord. O-25-03), a $325,000 (2,200 sq ft) new single-family home in Conway, AR has estimated permit fees of $275.00. This includes a $250.00 building permit fee and $25.00 plan review. Trade permits are billed separately.

Does Conway, AR calculate building permits by square footage or project valuation?

Conway prices new construction and additions by square footage under roof ($0.11 residential, $0.14 commercial) and remodels by valuation ($1.00 per $1,000). Electrical, plumbing and mechanical permits pulled with a building permit are a percentage of the building fee: 47% residential, 35% commercial, per trade.

How long does commercial plan review take in Conway, AR and what does it cost?

Plan review is a flat $25.00 for residential and commercial projects. The city does not publish a plan review turnaround time; ask the permit desk for the current queue when you submit.

Do I need an Arkansas commercial contractor license to pull a permit in Conway?

Yes, for commercial work of $50,000 or more. Under A.C.A. § 17-25-101, any project other than a single-family residence costing $50,000 or more in labor and materials requires an Arkansas Contractors Licensing Board commercial license, and the building official must see proof of license before issuing the permit. Residential builders and remodelers need an ACLB residential license for jobs over $2,000. Splitting a contract to stay under a threshold is not allowed. Licensed electricians, plumbers and HVACR contractors pull their own trade permits in Conway.

06

Sources and Assumptions

Schedule
Conway Code § 11.16.06 (Ord. O-25-03)
Source reviewed on
October 20, 2026
Data status
Fee schedule reviewed against the city's published source.

PermitBasis is an independent planning resource. The issuing authority determines final fees and requirements.