Skip to content
PermitBasis

Little Rock, AR · Pulaski County

Little Rock Residential Addition or Remodel Permit Fees and Submittal Checklist

An addition to, or alteration of, an existing one- or two-family dwelling.

01

Little Rock Fee Estimate

Fee Estimate

$

Permit valuation may differ from your construction budget when the city applies its own valuation method.

sq ft

Estimate · Little Rock, AR

$415.75

Estimated fees for the inputs shown. Conditional items are listed but not added.

Not included in this estimate

Plan review fee; Trade permits (electrical, plumbing, mechanical); utility tap and impact fees, re-inspection fees, and other agency approvals.

Cost of working without a permit in Little Rock: $1,170.00Permit fees are multiplied by 3× when work starts before the permit is issued.

Need sealed MEP drawings, permit expediting, or 3 bids from ACLB-licensed contractors in Little Rock?

Sources and Assumptions

Schedule
Little Rock Code § 8-31
Source reviewed on
October 20, 2026
Assumes
Residential occupancy; $90,000 valuation and 600 sq ft as entered.

PermitBasis is an independent planning resource. The issuing authority determines final fees and requirements.

02

Common Project Values

Estimated Little Rock fees for residential addition or remodel projects at six standard sizes, computed with the same rules as the calculator. Trade permits excluded.

  • Bath or porch

    $25,000 · 200 sq ft

    Permit fee $142.00

    $167.75

  • Single room

    $50,000 · 400 sq ft

    Permit fee $242.00

    $267.75

  • Primary suite

    $90,000 · 600 sq ft

    Permit fee $390.00

    $415.75

  • Two-room addition

    $150,000 · 900 sq ft

    Permit fee $570.00

    $595.75

  • Second story

    $250,000 · 1,400 sq ft

    Permit fee $870.00

    $895.75

  • Whole-house remodel

    $400,000 · 2,500 sq ft

    Permit fee $1,320.00

    $1,345.75

03

Central Arkansas Cost Comparison

The same project priced in all eight cities. Valuation-based cities (fee grows with project cost) and square-footage cities (fee grows with floor area) can differ widely for the same building. Full comparison →

04

Little Rock Submittal Checklist

Required and conditional documents for this project type. Confirm this requirement with the city.

Submittal Checklist0 of 6 ready
  1. Little Rock permit application

    Submit through Little Rock Planning & Development, Building Codes Division. Include the project address, parcel number, owner, contractor and declared valuation.

    Permit portal ↗
  2. Construction drawings

    Floor plan, foundation plan, wall section and elevations. Plans for one- and two-family dwellings generally do not require an architect's seal.

  3. Site plan or survey

    Property lines, setbacks, easements, building footprint, driveways and drainage. New commercial sites usually go through planning or site plan review first.

  4. Energy code compliance

    REScheck or equivalent showing compliance with the Arkansas Energy Code for the dwelling envelope.

    Arkansas energy code status ↗
  5. Arkansas contractor license verification

    Residential projects over $2,000 need an ACLB residential builder or home improvement license, unless the owner is building their own home.

    ACLB license lookup ↗
  6. Trade permits from licensed trades

    Electrical, plumbing and mechanical permits are pulled separately by Arkansas-licensed master electricians, plumbers and HVACR contractors.

Permit office

Little Rock Planning & Development, Building Codes Division

Confirm hours and submittal format with the city before you go.

Inspection Roadmap

  1. 1

    Footing

    After trenches are dug and steel is placed, before concrete

  2. 2

    Foundation / slab

    After under-slab plumbing, vapor barrier and steel, before the pour

  3. 3

    Rough-in: plumbing, electrical, mechanical

    After rough trade work, before walls are covered

  4. 4

    Framing

    After rough-ins pass, before insulation

  5. 5

    Insulation / energy

    After insulation, before drywall

  6. 6

    Trade finals

    Electrical, plumbing and mechanical finals

  7. 7

    Building final

    After all trade finals pass

05

Frequently Asked Questions

How much does a residential addition or remodel permit cost in Little Rock, Arkansas?

Under Little Rock Code § 8-31, a $90,000 (600 sq ft) residential addition or remodel in Little Rock, AR has estimated permit fees of $415.75. This includes a $390.00 building permit fee and $25.75 in administrative fees. Trade permits are billed separately.

Does Little Rock, AR calculate building permits by square footage or project valuation?

Little Rock calculates building permits by project valuation, not square footage. Work valued at $5,000 or less needs no building fee; above that, a base fee covers the first portion of value and a rate is added for each additional $1,000 or fraction. Valuation comes from the contract or the ICC Building Valuation Data table.

How long does commercial plan review take in Little Rock, AR and what does it cost?

Plan review costs 50% of the building permit fee (minimum $56.65) for commercial projects. The city does not publish a plan review turnaround time; ask the permit desk for the current queue when you submit.

Do I need an Arkansas commercial contractor license to pull a permit in Little Rock?

Yes, for commercial work of $50,000 or more. Under A.C.A. § 17-25-101, any project other than a single-family residence costing $50,000 or more in labor and materials requires an Arkansas Contractors Licensing Board commercial license, and the building official must see proof of license before issuing the permit. Residential builders and remodelers need an ACLB residential license for jobs over $2,000. Splitting a contract to stay under a threshold is not allowed. Licensed electricians, plumbers and HVACR contractors pull their own trade permits in Little Rock.

06

Sources and Assumptions

Schedule
Little Rock Code § 8-31
Source reviewed on
October 20, 2026
Data status
Some components are confirmed; unconfirmed components are marked Unavailable instead of estimated.
  • Ord. 22,703 (eff. Jan. 1, 2026) rewrote § 8-31(c) without a building valuation table; its other fees rose about 3%. Building fees here use the last published table (Ord. 22,204, 2022) until the city confirms the current one.
  • Residential fees in Targeted Neighborhood Enhancement Areas (Central High, Downtown, Philander Smith) are reduced 75%, not below the minimum. Not applied here.

PermitBasis is an independent planning resource. The issuing authority determines final fees and requirements.