Skip to content
PermitBasis

Sherwood, AR · Pulaski County

Sherwood New Commercial Construction Permit Fees and Submittal Checklist

A new commercial or multi-family building, measured by floor area under roof.

01

Sherwood Fee Estimate

Fee Estimate

$

Permit valuation may differ from your construction budget when the city applies its own valuation method.

sq ft

Estimate · Sherwood, AR

Unavailable

Sherwood does not publish this fee schedule. Known fees below total $375.00. Call (501) 835-4753 for a quote.

Not included in this estimate

Certificate of occupancy; Trade permits (electrical, plumbing, mechanical); utility tap and impact fees, re-inspection fees, and other agency approvals.

Need sealed MEP drawings, permit expediting, or 3 bids from ACLB-licensed contractors in Sherwood?

Sources and Assumptions

Schedule
Sherwood Code Title 11 (§ 11.04.07)
Source reviewed on
October 20, 2026
Assumes
Commercial occupancy; $750,000 valuation and 12,000 sq ft as entered.

PermitBasis is an independent planning resource. The issuing authority determines final fees and requirements.

02

Common Project Values

Estimated Sherwood fees for new commercial construction projects at six standard sizes, computed with the same rules as the calculator. Trade permits excluded.

  • Small scope

    $25,000 · 1,000 sq ft

    Unavailable

  • Mid scope

    $75,000 · 2,000 sq ft

    Unavailable

  • Standard

    $150,000 · 3,500 sq ft

    Unavailable

  • Commercial buildout

    $350,000 · 6,000 sq ft

    Unavailable

  • Major project

    $750,000 · 12,000 sq ft

    Unavailable

  • Large commercial

    $1,500,000 · 25,000 sq ft

    Unavailable

03

Central Arkansas Cost Comparison

The same project priced in all eight cities. Valuation-based cities (fee grows with project cost) and square-footage cities (fee grows with floor area) can differ widely for the same building. Full comparison →

04

Sherwood Submittal Checklist

Required and conditional documents for this project type. Confirm this requirement with the city.

Submittal Checklist0 of 11 ready
  1. Sherwood permit application

    Submit through Sherwood Engineering, Permits & Planning. Include the project address, parcel number, owner, contractor and declared valuation.

    Permit portal ↗
  2. Construction documents (digital PDF set)

    Architectural, structural, MEP and life-safety sheets. Under Arkansas law most commercial buildings need plans sealed by an Arkansas-licensed architect or engineer. Ask the city whether it accepts digital-only sets or also wants printed copies.

  3. Arkansas Fire Prevention Code review

    Commercial sets are reviewed for compliance with the Arkansas Fire Prevention Code (based on the IBC/IFC). Include life-safety plans, exit paths, fire-rated assemblies, and sprinkler and alarm shop drawings where provided.

    Arkansas State Fire Marshal ↗
  4. Site plan or survey

    Property lines, setbacks, easements, building footprint, driveways and drainage. New commercial sites usually go through planning or site plan review first.

  5. Energy code compliance

    COMcheck or equivalent showing compliance with the Arkansas Energy Code for envelope, lighting and mechanical systems.

    Arkansas energy code status ↗
  6. Central Arkansas Water availability and tap letter

    Confirm water and sewer availability and tap or meter fees with Central Arkansas Water. Tap and impact fees are not part of the building permit estimate.

    Central Arkansas Water ↗
  7. ADEQ construction stormwater permit

    Conditional

    Sites that disturb one acre or more need coverage under the ADEQ construction stormwater general permit and a stormwater pollution prevention plan.

    Applies when: One acre or more of land disturbance

    ADEQ stormwater ↗
  8. Floodplain development permit

    Conditional

    Required when any part of the work is in a FEMA special flood hazard area. Check the parcel on the FEMA map before design is final.

    Applies when: Parcel is in a mapped floodplain

    FEMA flood map ↗
  9. Arkansas Department of Health plumbing plan review

    Conditional

    Commercial plumbing and gas plans are reviewed by ADH (fee: 1% of the estimated plumbing and gas cost, $50 minimum, $500 maximum) unless a local certified plumbing inspector reviews engineer-prepared plans (A.C.A. § 17-38-204). Food service, medical and dental, child care and pools also need ADH program approvals.

    Applies when: Commercial plumbing work, food service, medical or similar uses

    ADH plumbing ↗
  10. Arkansas contractor license verification

    Commercial projects of $50,000 or more (labor and materials) need a contractor licensed by the Arkansas Contractors Licensing Board (A.C.A. § 17-25-101). The building official must see proof of license before issuing the permit.

    ACLB license lookup ↗
  11. Trade permits from licensed trades

    Electrical, plumbing and mechanical permits are pulled separately by Arkansas-licensed master electricians, plumbers and HVACR contractors.

Permit office

Sherwood Engineering, Permits & Planning

Confirm hours and submittal format with the city before you go.

Inspection Roadmap

  1. 1

    Footing

    After trenches are dug and steel is placed, before concrete

  2. 2

    Foundation / slab

    After under-slab plumbing, vapor barrier and steel, before the pour

  3. 3

    Rough-in: plumbing, electrical, mechanical

    After rough trade work, before walls are covered

  4. 4

    Framing

    After rough-ins pass, before insulation

  5. 5

    Insulation / energy

    After insulation, before drywall

  6. 6

    Fire and life safety

    Conditional

    Sprinkler, alarm and fire-rated assemblies before cover and at final

    When fire protection systems are part of the work

  7. 7

    Trade finals

    Electrical, plumbing and mechanical finals

  8. 8

    Building final

    After all trade finals pass

  9. 9

    Certificate of occupancy

    Issued after the building final; required before move-in

05

Frequently Asked Questions

How much does a new commercial construction permit cost in Sherwood, Arkansas?

Sherwood, AR does not publish the building permit fee and plan review fee for a $750,000 (12,000 sq ft) new commercial construction in a form PermitBasis can confirm, so no total is estimated. Known fees add $375.00. Call Sherwood Engineering, Permits & Planning at (501) 835-4753 for a quote.

Does Sherwood, AR calculate building permits by square footage or project valuation?

Sherwood prices new homes at $0.16 per square foot under roof. Fees for other building work come from a schedule the city adopted by reference but does not publish, so PermitBasis shows them as unavailable. Trade permits are billed per item (openings, fixtures, equipment).

How long does commercial plan review take in Sherwood, AR and what does it cost?

Sherwood does not publish a plan review fee. The city does not publish a plan review turnaround time; ask the permit desk for the current queue when you submit.

Do I need an Arkansas commercial contractor license to pull a permit in Sherwood?

Yes, for commercial work of $50,000 or more. Under A.C.A. § 17-25-101, any project other than a single-family residence costing $50,000 or more in labor and materials requires an Arkansas Contractors Licensing Board commercial license, and the building official must see proof of license before issuing the permit. Residential builders and remodelers need an ACLB residential license for jobs over $2,000. Splitting a contract to stay under a threshold is not allowed. Licensed electricians, plumbers and HVACR contractors pull their own trade permits in Sherwood.

06

Sources and Assumptions

Schedule
Sherwood Code Title 11 (§ 11.04.07)
Source reviewed on
October 20, 2026
Data status
Some components are confirmed; unconfirmed components are marked Unavailable instead of estimated.
  • Work without a permit is a misdemeanor with fines of $100–$500 per offense (§ 11.01.04); no fee multiplier is published.
  • Fees for work other than new homes come from the schedule attached to Ord. 1599 / Ord. 2057, which is not published online. Re-inspection is $25.

PermitBasis is an independent planning resource. The issuing authority determines final fees and requirements.